Hi friends,
This is my client requirement.
My client wants to assign four operations in Routing for producing Finished material .
In four operations, client wants to put quality check on 2nd and 4th operation only.
For in process, 2nd and 4th operations quality check I can give control key "PP04--In house Production for Inspection" by
assigning "MIC" .
and After creation & release of production order inspection lot is created.
During Results Recording and Usage Decision the system is allowing to do the confirmation for the 2nd Operation
by using T-code: CO11N
but when we go for confirming the 4th operation the system is not providing us with the required Inspection Lot
so that the In Process inspection can be continued / completed.
Please suggest